Contact SupplierEngineering Construction Division (ECD) which has a very significant presence in the nuclear sector, is an important business vertical of Avasarala providing services. ECD has taken a wide spectrum of projects ranging from critical and quality intensive programs like reactor life extension to quantity intensive supply and erection programs like cable tray installation projects.
We have the unique distinction of undertaking projects in radiation environment with several records to our credit for containing the radioactive dosage level to the lowest through very effective automation.
Â
EPC services:
On site services:
Projects undertaken:
CALANDRIA AND END SHIELD INSTALLATION:
A site work executed during a 220MWe nuclear power plant construction. Installation involved 1 No. Calandria, 2 Nos. End shields, 1No. Ion chamber, filling of steel balls in end shields, liner work inside calandria vault.
Â
Fabrication of special lifting tools and tackles, load test certification prior to using was part of work.
Â
Criticalities:
The installation was completed by engineers and technicians in a record time of 44 weeks. Seamless coordination with various agencies adhering to the elementalised time schedule was the essence of the execution of work.
Â
REACTIVITY CONTROL MECHANISM:
Employed for controlling and regulating reactivity level inside calandria of 220 MWe reactor. Functions include Drive – In and Drive –Out of the neutron absorbing elements in the reactor core. Works on the principle of winding of rope over sheave using a controlled electric motor. The Unique feature is minimizing of wear particles due to rubbing / rolling of metal to metal parts thus reducing reactor contamination particularity of undesirable element.
Â
Criticalities
Execution of this involved modelling and preparation of engineering drawings from concept design. Extensive planning and engineering, establishing intricate stainless steel castings, forgings. Machining carried out in separate cells to ensure non-contamination of carbon steel. Assembly and cold run tests to demonstrate 30 million cycles at various working simulated parameters executed by setting up a 15 meters high working platform. Actual flow at elevated temperature simulated to ensure fault free working. The unit is installed and commissioned at site.
Â
EN MASSE COOLENT REPLACEMENT
As the reactors reach an end of life, its life is further enhanced by carrying out the critical re-furbishing work which ensures and extends the life of the reactor. This work is carried out during the typical shutdown period which consists of replacement of all Coolant Channel items and installation of new pressure tubes and associated items. The Work is carried out in a radiation environment with a dosage rate varying between 250 milli–Rems/hour to 100 milli-Rems/hour. A manpower intensive campaign involving minute planning, scheduling & training of skilled operators with critical monitoring of the allowable radiation dosage. Testing prior to hand over inspection and recording of measurements. Norms prescribed by AERB are applicable.
Â
Criticalities
Innovative powered automation devices introduced to reduce radiation exposure and to improve productivity. Extensive training of operators in a full scale mock set-up adapted. The cumulative radiation dosage of 575 man-Rems was achieved. The work was completed in 10 months. The expertise gained has resulted in achieving successful repeat performance in other locations and projects.
Â
Engineering Procurement and Construction – EPC is a part of Avasarala Group, which specializes in taking up various works in the Nuclear Island.